Sea Solutions NV Completes First Beach Maintenance Project in Aruba

godking
22 January 2008 12:01am

Thanks to the island’s government, Moomba Beach Bar, Holiday Inn Sunpress Resort, and Playa Linda Beach Resort a giant project of beach maintenance was just concluded on Aruba’s famed Palm Beach.

The first portion of ocean front to be scoured was the one in front of Moomba Beach, where a stretch of 60 x 50 meters of swimming area was completely restored in three stages, a process which took 25 working days.

During the first 10 days Sea Solutions N.V. used a net to remove all plastic, aluminum, seaweed, and waste that doesn’t belongs in a natural sea environment, and to bring it to the surface and bag it ready for delivery to the dump. In this process approximately four tons of non-organic matter and seaweed emerged from the bottom of the sea.

In the next phase which also lasted 10 days Sea Solutions N.V. used a suction pump to remove approximately 600 cubic yards of mud from the ocean floor. The mud, a natural organic sediment, which serves as a very good nutrient for sea life, was discharge at sea, far away from the intake point and the swimming areas.

In the third phase which lasted for five days Sea Solutions N.V. pumped in 300 cubic yards of clean sand into that same area where the mud was removed forming an unspoiled white coat of sand at the bottom area.

At the end of 25 work days the beach was totally recuperated and ready for visitors and locals who enjoy it, in its pristine state.